As of the beginning of November, the construction project is 45% complete. The month of October was a large push to complete the shell structure of the Parish Activity Center, and to begin to close up the building. Structural steel, joists, and roof decking were erected, then concrete slabs on deck were poured for the roof in the north building area and for the second level floors in the Preschool and north classroom areas. Roofing started in late October, and will continue into November.
The morning of Wednesday, November 10, we had over 20 construction workers laying the concrete flooring of the parish activity center. It's so exciting to see things coming together!